Installing ridge cap shingles on a hip roof is important for both aesthetics and keeping your roof watertight. As part of a shingle roof installation, the caps go on last, after every field shingle is down. You cap each hip first, starting at the eave and working up toward the peak. Then you cap the main ridge, starting at the end opposite the prevailing wind. Each cap piece gets bent over the hip, set at the exposure the manufacturer lists, and nailed so the next piece hides the fasteners.
Key Takeaways
|
Before You Start Capping a Hip Roof
A few decisions made on the ground save a lot of fixing on the roof. Run through these before you carry the first bundle up the ladder.
- Pick the right cap product: most shingle makers sell hip and ridge shingles built for the job. Laminated architectural shingles are too thick and stiff to cut into caps that bend cleanly, so don’t try. Three-tab shingles can be cut into caps when they match the roof.
- Check lot numbers: cap bundles from different production lots can vary slightly in color, which shows up fast on a long ridge.
- Watch the temperature: shingles get brittle below about 40°F and can crack when bent. Keep cap bundles somewhere warm until you need them, and never “break” a bundle over the ridge to soften it.
- Plan for the ridge vent: if the ridge has a vent, the caps go over it, and you’ll need longer nails to reach through the vent into the deck.
- Re-roofing? Tear off the old hip and ridge caps first. Capping over them leaves a lumpy line that won’t seal well.
Steps To Install Ridge Cap Shingle On A Hip Roof
Follow these instructions to begin with the ridge cap shingle installation process:
1. Gather the Equipment and Material
- Hip and ridge cap shingles (or cut three-tab pieces that match the roof)
- Corrosion-resistant roofing nails: galvanized, stainless, or aluminum, with at least a 3/8-inch head and long enough to go 3/4 inch into the deck
- Asphalt roof cement for hand-sealing and covering exposed nails
- Hammer or roofing nailer
- Utility knife with a hook blade
- Chalk line
- Measuring tape
- Gloves
- Harness
Having everything in place before starting will prevent time wastage and interruptions during the installation.
2. Roof Ridge Preparation
Preparations are also essential to ensuring a smooth installation process.
- Finish the Field Shingles: every shingle on the roof planes should be installed and trimmed along the hips and ridge before any caps go on.
- Clean the Hips and Ridge: sweep off granules, cut scraps, and nails so the caps sit flat.
- Snap Guide Lines: snap a chalk line a few inches down from the peak on one side of each hip and the ridge. It keeps the caps running straight instead of wandering.
3. Measure and Cut the Shingles
Proper measurements and cuts ensure the shingles fit perfectly along the ridge.
- Count What You Need: Measure each hip and the ridge, then divide by the cap exposure to estimate how many pieces you’ll need. Add a few extra for starter and finishing pieces.
- Separate or Cut the Caps: Most hip and ridge products are perforated, so you simply snap them into individual pieces. When using three-tab shingles, cut them into individual pieces of ridge caps. Each piece should have straight, clean edges on both sides.
- Make a Starter Piece: Cut the exposed portion off one cap so only the back half remains. This short piece goes at the bottom of each hip and gives the first full cap something to lap over.
4. Install the Hip Caps First
Work one hip at a time, from the eave up to the ridge.
- Start at the Bottom of the Hip: set the starter piece at the eave, bent evenly over the hip, and nail it. Lay the first full cap right over it.
- Keep a Consistent Exposure: set each cap so the same amount shows on every piece, usually 6 to 8 inches depending on the product. Follow the exposure printed on the bundle rather than guessing.
- Nail Each Cap Correctly: drive one or two nails on each side, about 1 inch in from the side edge, at the distance back from the exposed end listed on the bundle. The next cap should cover those nails completely.
Nails must go in straight and sit flush. A nail driven at an angle or sunk too deep cuts the shingle and can back out or let water in. If you’re using a nail gun, test the pressure on a scrap first.
5. Install the Ridge Caps
Once all the hips are capped, move to the main ridge.
- Start Opposite the Prevailing Wind: begin at the end of the ridge that faces away from the usual wind, so the wind blows over the cap edges instead of into them.
- Follow the Chalk Line: keep the caps lined up with your guide line so the ridge looks straight from the street.
- Lap Over the Hips: where the ridge meets the hips, the ridge caps should run over the tops of the hip caps, never under them.
- Press the Seal Strips: press each cap down firmly so the factory sealant strip makes good contact.
6. Seal and Inspect the Ridge
Carry out final sealing and inspection at the ridge to ensure a clean and long-lasting installation.
- Cover Any Exposed Nails: The final cap is face-nailed, so dab roof cement over those nail heads. Use cement sparingly, since too much can blister the shingle.
- Hand-Seal in Cold Weather: If it’s chilly and the strips won’t seal on their own for a while, add a few quarter-sized dabs of roof cement under each cap.
- Trim Excess Material: If excess shingle material is present, trim it neatly.
- Inspect Closely: Inspect the entire ridge for gaps, loose shingles, or misalignment. Make corrections as needed.
Handling the Peak and the End of the Ridge
The two spots that trip people up on a hip roof are where the hips meet the ridge and the very last cap. Both are easy once you know the trick.
Where the Hips Meet the Ridge
Bring each hip cap right up to the peak and trim the top piece so it lies flat over the ridge line. When the ridge caps go on, the first ridge piece covers the tops of those hip caps. On a pyramid-style hip roof, where all the hips meet at one point, many roofers finish with a cap piece cut and bent to cover the center, then nail it and seal the nail heads.
Finishing the Last Ridge Cap
The last piece is where many ridges fail, because there’s no next cap to cover its nails. Cut the final cap from the exposed portion of a full piece so no unprotected back section shows. Fit it to the end of the ridge and face-nail it about 1 inch in from each side edge and from the end. Then cover the nail heads with a small dab of roof cement.
Common Installation Problems
- Lack of Alignment: Misalignment is a common issue in shingle installation. The chalk line has to be perfectly drawn for the desired results.
- Wrong Exposure: Too much exposure leaves nails uncovered, and too little wastes material. Stick to the exposure listed on the cap bundle.
- Capping in the Wrong Order: Laying the ridge before the hips, or starting the ridge into the wind, leaves joints that catch water and wind.
- Poor Nailing: Short nails, nails driven at an angle, overdriven nails, and nails placed too close to the exposed end all cause leaks or blow-offs.
- Damaged Shingles: Cracked shingles or wrong cuts to the shingles do not make for a strong ridge. Handle your shingles well and replace all damaged pieces.
- Too Much Roof Cement: Small dabs help in cold weather, but heavy globs can blister the shingle and look messy. Let the nails and seal strips do the main work.
Conclusion
Ridge cap shingles help a hip roof withstand weather changes while enhancing its appearance. The order matters most: field shingles first, then each hip from the eave up, then the ridge starting away from the wind. Keep the exposure even, drive nails straight and flush where the next cap will hide them, and seal the final piece. Do that, and the caps will shed water and hold up in strong wind for years.
Hip roofs have more ridgelines, and more places for a small mistake to turn into a leak. If you’d rather leave the ladder work to a pro, the roofing contractors at Precision Roofing and Exteriors can cap your hips and ridge cleanly as part of a new roof or a repair. Reach out for a free estimate.
FAQs
Do you install hip caps or ridge caps first?
Hips first. Cap each hip from the eave up to the peak, then install the ridge so its caps lap over the tops of the hips. That order keeps water running over the joints instead of into them.
Which direction should ridge cap shingles face?
Start at the end of the ridge opposite the prevailing wind and work toward the wind. That way the exposed edge of each cap faces away from the wind, so gusts don’t lift it.
How many nails go in each ridge cap shingle?
Most products call for at least one nail on each side, about 1 inch in from the side edge. In high-wind areas, many manufacturers call for two nails per side. Always follow the pattern printed on the bundle.
Can you use architectural shingles as ridge caps?
It’s not recommended. Laminated architectural shingles are thick and can crack when bent over a hip. Use the hip and ridge shingles made to match your roof instead.